Chapter 5 of 7 Payments 6 min read

Retention and stage payments: paying a builder safely

The safest way to pay for building work is in stages that match work actually done, with a small amount held back until defects are fixed. This chapter explains deposits, stage payments and retention, with worked numbers and the current position on the proposed ban on retentions.

In this chapter
  1. The principle: pay for progress, not promises
  2. Deposits
  3. Stage payments
  4. How retention works
  5. Keeping a payment record
  6. The final account
  7. Paying less than asked
  8. The proposed ban on retentions
  9. Common questions

The principle: pay for progress, not promises

At any point in the job, the money you have paid should be no more than the value of the work done and materials delivered to site. If the builder walks away tomorrow, you want to be able to pay someone else to finish without having paid twice. Stage payments and retention are how a contract keeps you there.

Deposits

A deposit is a payment before work starts. For domestic work it is common for builders to ask for something, usually to cover materials with long lead times such as windows, steels or a kitchen.

In our worksheet the deposit is credited back across the stage payments, so the total you pay still equals the contract sum.

Nearly finished open-plan kitchen extension with black-framed glazed doors to a small garden, one wall still bare plaster and masking tape on a window frame
Nearly finished is not finished. The retention is your leverage to get the last items and any defects done.

Stage payments

There are two common ways to pay during the build:

Milestones need clear definitions. "Roof complete" should say whether it means structure, covering, rooflights and gutters, or just the structure.

An example milestone plan for a single-storey extension
MilestoneShare of contract sumWhat must be true
1. Foundations and slab15%Building control has inspected foundations, slab cast, drains tested
2. Walls to plate height25%Walls built, steels in, cavity insulation in place
3. Watertight25%Roof covered, windows and doors fitted and locking
4. First fix and plaster20%Wiring and pipes run, walls plastered, screed laid
5. Practical completion15%All work complete, certificates supplied, site clear

Notice the last stage is substantial. A plan that leaves only 5% for the end gives the builder little reason to finish the snagging.

How retention works

Retention is a percentage of each payment that you hold back as security against defects and unfinished work. In UK construction it is typically 3% to 5%. Half is usually released at practical completion and the rest at the end of the rectification period, once defects are fixed.

Under JCT Minor Works the default retention is 5% of interim payments, reducing to 2.5% at practical completion. The JCT Home Owner contracts handle the final payment differently, and many domestic builders propose their own terms. Whatever the form, write down:

Worked example: £60,000, four stages, 5% retention, 6 months

  • Each stage is worth £15,000. You hold back 5%, £750, and pay £14,250.
  • After four stages you have paid £57,000 and hold £3,000.
  • At practical completion you release half: £1,500.
  • Six months later, once defects are fixed, you release the final £1,500.
  • Total paid: £60,000, exactly the contract sum.

Run your own numbers, including a deposit and custom stage percentages, in the payment schedule worksheet.

Is 5% enough? Retention is not meant to fund a full repair job. It is an incentive for the builder to come back. On a £60,000 job, £1,500 is enough to make a builder return for a sticking door or a cracked bead, not to rebuild a leaking roof. For serious defects you rely on the contract and the builder's liability, which continues well beyond the rectification period.

Keeping a payment record

Keep a simple running record from the first payment. For each one note the date, the stage or valuation it relates to, the gross value, the retention held, any deposit credit and the amount paid. Our payment schedule prints in exactly this format. It takes a few minutes per stage and settles most arguments about what has been paid before they start.

The final account

Before the last payment, agree a final account: the contract sum, plus or minus every variation, with provisional sums replaced by actual costs. Make sure every variation was priced or recorded at the time. Disputes about the final account are much easier to avoid than to resolve.

Paying less than asked

If a stage is claimed but not complete, or work is defective, you can pay less, but do it properly. Under JCT forms, you must give a pay less notice by the deadline in the contract, stating what you will pay and why. Under the Home Owner contracts the procedure is simpler but should still be in writing. Never just stop paying without explanation; it hands the builder a grievance and can justify them suspending work.

The proposed ban on retentions

The government has committed to banning retention clauses in construction contracts. The Commercial Payments Bill was introduced in the House of Lords in May 2026, completed its Lords stages on 20 October 2026 and had its first reading in the Commons on 21 October. On 2 November 2026 it is not law; Commons second reading has no date yet. Even after Royal Assent, the retention provisions take effect only from a commencement date the government will set. Two points matter for homeowners:

The Bill also makes clear that genuine staged payments remain allowed. If retention does disappear from your contract, a well-designed stage plan with a meaningful final stage, and a clear defects procedure, does most of the same job.

Common questions

What is a normal retention percentage for a house extension?

3% to 5% of the contract sum is typical. JCT Minor Works defaults to 5% reducing to 2.5% at practical completion. Some small builders resist retention; a strong final stage payment is an alternative.

When should retention be released?

Usually half at practical completion and the rest at the end of the rectification period once defects are fixed. The rectification period is commonly 6 or 12 months on homes.

Can the builder refuse to fix defects and just forfeit the retention?

They can try, but their obligation to fix defects in the rectification period, and their wider liability for defective work, does not end because you hold money. Retention is security, not a cap on liability.

Should I pay in cash for a discount?

No. You lose a clear payment record, any card protection, and you may be helping the builder evade tax. Pay by bank transfer against a written invoice for each stage.