Chapter 7 of 7 Approvals 6 min read

Building control and party walls: the approvals beside your contract

Your building contract deals with you and the builder. Two other processes run alongside it and can stop work if they are missed: building regulations approval and, if you build near a neighbour, the Party Wall Act. Here is what each requires and who should do it.

In this chapter
  1. Three separate permissions
  2. Building control: the routes
  3. The Party Wall etc. Act 1996
  4. Talking to neighbours first
  5. Where planning fits in
  6. Writing it into the contract
  7. Common questions

Three separate permissions

People often confuse these. They are independent, and you might need all three:

Planning, building regulations and party wall compared
RegimeAsksWho decides
Planning permissionIs the development acceptable in this place? Appearance, size, neighbours' amenityLocal planning authority (or permitted development rules)
Building regulationsIs it built safely? Structure, fire, insulation, drainage, ventilationLocal authority building control or a registered building control approver
Party Wall ActAre the neighbour's building and rights protected?You and your neighbour, or appointed surveyors if you cannot agree

A builder's contract cannot remove any of these duties, but it should say who handles each one. The JCT Home Owner contracts include a section for exactly this.

Building control: the routes

Almost every extension needs building regulations approval. You can use your local authority building control or a registered building control approver (a private firm). Either way there are three ways to apply:

Inspections happen at key stages: foundations, damp proof course, drains, structure, insulation and completion. At the end you receive a completion certificate (or final certificate from an approver). Keep it: you will need it when you sell. Some work, such as electrics or replacement windows, can instead be signed off by the tradesperson, provided they belong to a government-authorised self-certification scheme.

Do not accept "building control isn't needed". For an extension it almost always is. Without approval, the building control body can require you to alter or remove work, and a missing completion certificate causes problems on sale.

Fees

Fees are set by each local authority or approver, not nationally. For a single-storey extension under about 40 m², total building control fees in England are often somewhere around £800 to £1,500 including VAT. Get the figure for your area and decide in the contract who pays it. Builders often exclude it.

Duty-holders

Since October 2023, building regulations in England include duty-holder roles: the principal designer and principal contractor for building regulations purposes. On domestic projects these normally fall to your designer and builder, not you, provided you appoint them. The JCT 2024 contracts record who holds each role.

Local Authority Building Control on full plans applications versus building notices, inspections and the completion certificate. Filmed in 2013: the process is the same, but the private route is now called a registered building control approver and a full plans decision can take up to five weeks, or two months if you agree.

Video by LABC. Open it on YouTube. YouTube is contacted only when you press play, through its reduced-tracking youtube-nocookie domain.

A single extension followed through its building control inspections to the completion certificate. Also filmed in 2013, so fees and some terms have moved on, but the inspection stages are still the ones you will see.

Video by LABC. Open it on YouTube. YouTube is contacted only when you press play, through its reduced-tracking youtube-nocookie domain.

Rear extension under construction on a brick semi-detached house, close to the neighbour's fence, with scaffolding and new walls
Building close to a boundary often brings both regimes into play: building control for the structure, the Party Wall Act for the neighbour.

The Party Wall etc. Act 1996

The Act applies in England and Wales when you:

Most rear extensions next to a neighbour trigger the excavation rule, because new foundations are usually deeper than old ones.

Party Wall Act notice periods
Type of noticeMinimum notice before workNeighbour must respond within
Party structure notice (work to an existing party wall)2 months14 days
Line of junction notice (new wall at the boundary)1 month14 days
Adjacent excavation notice (3 or 6 metre rule)1 month14 days

Notices are valid for a year. If a neighbour does not reply within 14 days to a party structure or excavation notice, a dispute is treated as having arisen, and surveyors are appointed to agree a party wall award. As the building owner you normally pay the reasonable costs of both surveyors, so a single agreed surveyor is usually cheapest. Talking to your neighbour before serving notice is the best way to get written consent and avoid surveyor costs altogether.

Timing it into your programme

If your builder can start on 1 June and the work needs a party structure notice, serve it by 1 April at the latest. Allow longer if a dispute is likely: a surveyor's award can take several weeks after appointment. Put the start date in the contract only after you know the party wall position, or make it subject to the award.

Talking to neighbours first

Party wall disputes usually start with surprise, not with the works. A conversation before any notice arrives makes consent far more likely. Practical steps that help:

If your neighbour still wants a surveyor, suggest an "agreed surveyor" acting for both of you. The fee is typically a fraction of two separate surveyors. Fees vary widely, so ask for a fixed quote; a single award for a straightforward rear extension is often in the region of £900 to £1,500 per surveyor in 2026, more in London.

Where planning fits in

Many single-storey rear extensions in England can be built under permitted development rights without a planning application, within limits on depth, height and materials, and some larger ones under the prior approval process. Flats, maisonettes, listed buildings and some conservation areas have restricted rights. Before relying on permitted development, check the Planning Portal guidance on extensions and consider applying for a lawful development certificate for certainty. Building regulations and the Party Wall Act still apply in full even when planning permission is not needed.

Writing it into the contract

  1. Who applies for building regulations approval, and who pays the fees.
  2. Who books inspections (usually the builder) and who receives the completion certificate.
  3. Who serves party wall notices (you, or your surveyor on your behalf) and that work affected will not start until notices and any award allow it.
  4. That the builder will comply with any party wall award, including access times and protection.
  5. That practical completion requires the building control completion certificate, or an agreed alternative.

Other approvals can appear in the same list: sewer consent from the regional water and sewerage company when the footprint sits over or close to a public sewer, and listed building consent for a listed home.

Common questions

Does my builder or my architect apply for building regulations?

Either can, and on design and build the contractor usually does. On the traditional route your architect usually submits the full plans application. Whoever applies, the contract should say so.

Do I need a party wall surveyor?

Not if your neighbour consents in writing to your notice. You need surveyors only if a dispute arises. You can serve notice yourself using the template letters in the government's explanatory booklet.

Can work start before the party wall notice period ends?

Only if the neighbour agrees in writing to an earlier start.